Protect America’s Backcountry Forests from Roadless Rule Rollbacks! Read More →×

Lopez Dam: Setting the Record Straight

16 min read


Below we provide updates on the latest developments in the ongoing Lopez Dam litigation including recent court rulings, and answer common questions about what this case means for our region’s water security and wildlife protections.

What is this case all about?

For decades, San Luis Obispo County has operated Lopez Dam and Reservoir without the necessary water rights permit. The County’s current permit effectively only allows the County to store water in the reservoir, but not to convey water from the reservoir to local water users. To comply with both state and federal law, the County must obtain a water rights permit that will allow it to legally deliver water to local users. To get such a permit, the County must also comply with the federal Endangered Species Act and various state law requirements and develop a complete and adequate plan for operating the reservoir in a balanced fashion that protects fish and wildlife while also meeting water supply needs.

Despite nearly 30 years of warnings, the County has failed to develop the plans needed to secure its water rights permit and related federal Endangered Species Act permit and has failed to take the necessary actions to protect fish and wildlife from harms associated with reservoir operations.

In response, ForestWatch and partners took legal action to compel the county to finalize the permit and ensure long-overdue protections for steelhead and other endangered and threatened species. In November 2024, in response to overwhelming factual evidence,  a federal judge issued a preliminary injunction requiring the County to implement interim water releases and habitat improvements to protect the environment while a final decision is reached. The injunction also required the County to submit a detailed Habitat Conservation Plan to the federal wildlife agencies by October 2025.

Despite the ruling’s temporary nature, the County chose to appeal rather than collaborate on a long-term solution. While the appeal was pending, in October 2025, the County submitted a draft Habitat Conservation Plan to the federal wildlife agencies. Unfortunately, the draft plan is woefully inadequate to protect imperiled wildlife in Arroyo Grande Creek and thus is unlikely to gain full approval from the federal agencies.

In December 2025, the U.S. Court of Appeals for the Ninth Circuit vacated the preliminary injunction and sent the case back to the District Court for further review. The Ninth Circuit did not overturn the finding that the County is likely violating the Endangered Species Act or reject the need for improved protections. Instead, it directed the District Court to conduct a more complete analysis of impacts to all protected species before determining whether interim water releases should be required.

Did the County win the appeal?

The County has described the Ninth Circuit decision as a major victory, but that characterization is misleading. The Ninth Circuit’s decision did vacate the preliminary injunction. It did not:

  • overturn the finding that the County is likely violating the Endangered Species Act
  • determine that current dam operations are lawful
  • reject the need for increased flows or other protections for wildlife

Instead, the Ninth Circuit’s ruling requires the District Court to more fully evaluate how potential remedies could affect multiple protected species before ordering mandatory interim changes.

In effect, the decision mainly prolongs and adds complexity to the case, greatly increasing costs without resolving the underlying legal issues.

Why hasn’t this case been resolved yet?

Los Padres ForestWatch and its partners have consistently been open to reaching a settlement that would resolve the case and bring Lopez Dam into compliance with the law.

However, a meaningful resolution requires a serious commitment to providing adequate flows for steelhead and other species downstream of the dam. To date, the County has not engaged in that core issue in a way that would allow for a durable agreement.

Instead, the County has continued to pursue a litigation strategy that focuses on delay and procedural arguments rather than resolving the underlying legal violations. As a result, the case has moved forward in court with little progress towards potential settlement.

We believe that avoiding prolonged litigation is in the public interest. However, any resolution must address the fundamental requirement to protect threatened and endangered species and secure the permits the County needs to lawfully operate the dam.

What are the costs on continued litigation?

Continuing down the current path is expected to significantly increase costs for the County and the communities it serves.

The next phase of litigation in District Court will be more complex and resource-intensive. If the County continues to pursue litigation rather than settlement, total costs are expected to grow substantially beyond what has already been spent.

If the court ultimately affirms that the County is violating the Endangered Species Act, federal law requires that prevailing plaintiffs recover their attorneys’ fees and costs. Plaintiffs are pursuing this case on a contingency basis, meaning our attorneys are only compensated if they prevail. Recovering those costs makes this type of public interest enforcement possible. Unfortunately, those costs continue to increase as the County prolongs the case rather than resolving the underlying issues. The County is likely to pass these expenses on to Zone 3 ratepayers.

In addition, the County’s current approach does not resolve the underlying issue. Even after years of litigation, the County would still need to complete a lengthy federal permitting process to bring the dam into compliance. As noted above, the County’s draft Habitat Conservation Plan is woefully inadequate and thus will likely require revisions before even initiating that permitting process.

Taken together, this creates a scenario where public funds are spent on prolonged legal proceedings rather than on implementing a solution that addresses both water reliability and environmental requirements.

What happens next?

The case is now moving forward in District Court.

If the case does not settle, the court will:

  • review additional scientific and expert evidence
  • evaluate impacts to multiple protected species
  • determine whether increased water releases or other measures are required to comply with the Endangered Species Act

This case has already driven meaningful progress. The litigation brought long-standing legal issues into the open and compelled the County to begin developing a Habitat Conservation Plan, a necessary step toward legal compliance.

Los Padres ForestWatch and its partners remain actively engaged and focused on achieving a durable outcome. We continue to participate in the legal process while remaining open to a settlement that provides real protections for wildlife, ensures long-term water reliability, and avoids unnecessary public expense.

What does the preliminary injunction do?

The preliminary injunction was a temporary court order requiring San Luis Obispo County to implement interim measures to protect threatened steelhead trout while the lawsuit is ongoing. This included a requirement to release modest, specific amounts of water from Lopez Dam to ensure steelhead migration in Arroyo Grande Creek

The order also required the County to submit a Habitat Conservation Plan to federal wildlife agencies by October 1, 2025. That plan has now been submitted, marking an important step toward compliance with the Endangered Species Act. However, it represents only the beginning of a longer federal review and approval process that may take several years. Securing an approved plan and the associated permits remains necessary for the County to lawfully continue delivering water from the reservoir to local users.

This ruling did not permanently determine how the dam must be operated—it simply ensured improvements to habitat conditions for endangered species in the short term while long-term solutions are developed.

In December 2025, the Ninth Circuit vacated the preliminary injunction and returned the case to the District Court for further analysis. The County reverted its operation of the dam to releasing the more limited amount of water to Arroyo Grande Creek, as it was doing prior to the lawsuit. As a result, there are currently no interim protections in effect while the court reconsiders the appropriate remedy.

Why was the preliminary injunction notable?

Winning a preliminary injunction was significant because courts require strong, compelling legal and factual evidence before granting one. To succeed, we had to demonstrate that irreparable harm to steelhead would occur without immediate intervention and that our legal claims were likely to succeed at trial. This ruling affirmed that the County’s operations likely violate the Endangered Species Act by harming steelhead, and it underscored the urgency of protecting steelhead while a final resolution is reached.

Although the injunction has been vacated for now, the underlying findings remain significant. The case now proceeds with that foundational understanding intact, as the District Court evaluates the appropriate path forward.

What science and data did the court rely on to set temporary water release?

The preliminary injunction ruling set temporary water release requirements based on the County’s own consultants’ analysis, which determined the flows necessary to support steelhead migration and habitat. The District Court relied on scientific data and expert recommendations to ensure compliance with the Endangered Species Act. Notably, over 20 years ago the County committed to federal and state resource agencies that it would implement a similar temporary water release program, but then declined to do so.

Did the preliminary injunction threaten the local water supply?

No. The preliminary injunction was temporary and ensured threatened steelhead received adequate flows while a final solution is developed. Lopez Reservoir was near full capacity, making the county’s claim that the ruling threatens water supply during the short time it would be in effect false. The court-ordered flows were proportionally small compared to other existing water demands, including municipal, agricultural, and discretionary releases. The County’s assertion that these requirements were permanent suggested it in fact had no real intention of finalizing a wildlife protection plan with wildlife agencies, further affirming our original motivation to legally intervene.

Did the ruling impact the fire department’s ability to respond to wildfire?

No, these wild assertions play off of the current political climate to spread fear and misinformation. The ruling did not impact the fire department’s ability to respond to wildfires. Lopez Reservoir was near full capacity, and fire agencies have multiple water sources available for firefighting. The County’s claim that the court-ordered releases jeopardize fire suppression is misleading and ill-informed. Consider that the largest helicopter fire buckets hold about 2,600 gallons. At 5% of its capacity, Lopez Lake would provide enough water for over 300,000 drops of water from helicopters. Again, the required flow adjustments were proportionally small, temporary, and did not diminish emergency response capabilities.

Indeed, authorities successfully fought the recent large Gifford fire in land near Lopez Reservoir without significant impact to the amount of water stored in the reservoir. As is publicly reported on the County’s website, the reservoir remains substantially full.

Who is really using the most water, and why is wildlife being blamed?

Before pointing fingers at wildlife protections, the County should take a closer look at where the bulk of the water from Lopez Reservoir is actually going. According to publicly available data housed by the State Water Resources Control Board, in 2021 and 2022, a single private agricultural entity diverted more water from Arroyo Grande Creek than the combined municipal demand of all five cities that rely on Lopez Reservoir! Yet, the County claims that modest, science-based flow releases for steelhead are the problem. The real question isn’t whether we can balance wildlife needs; it’s why a small number of private interests are receiving the lion’s share of water while the County fights protections that benefit the entire ecosystem and community. Instead of attacking steelhead protections, we should be asking whether our water is being equitably managed for everyone.

What solutions are the county ignoring while pointing fingers?

Before our citizen suit, the County was following its Interim Downstream Release Plan which included a Low Reservoir Response Plan that only kicks in after Lopez Reservoir is already 60% depleted, instead of taking proactive steps to manage water sustainably before shortages occur. The County’s approach did not discuss how conservation efforts could reduce demand or how investments in groundwater recharge and other water supply augmentation projects could help secure long-term resilience. Instead of working toward forward-thinking solutions, the county is using steelhead protection as a scapegoat while ignoring the bigger issue of outdated, reactionary water management policies that put the region at greater risk. If the County truly wanted to address water security, it would be focusing on smart conservation, efficiency, and diversified water solutions, all of which will be required for the County to secure the legal right to continue using Lopez reservoir—instead of fighting environmental protections.

Who pays for the County’s legal delay tactics?

Residents of the Five Cities are paying for the County’s legal fight over Lopez Dam, even though the San Luis Obispo County Board of Supervisors decides whether to settle or continue litigating. So far, more than $3 million in taxpayer money has gone to litigation defense costs—many times more than the amount the County has invested over the past 26 years in developing the environmental study and habitat restoration projects that are necessary to bring dam operations into compliance with the law.

Instead of funding solutions, the County’s lawyers are currently arguing in court that Lopez Dam does not impact steelhead trout. This claim directly contradicts decades of findings from state and federal wildlife experts, as well as the County’s own consultants.

Did steelhead once thrive in Arroyo Grande Creek?

Yes. Arroyo Grande Creek historically supported a thriving steelhead trout population that was central to the creek’s ecology and local recreation.

  • Early Abundance
    Historically, Arroyo Grande Creek had a robust, self-sustaining steelhead population and the creek was popular with anglers fishing for steelhead. As many as 25,000 adult steelhead more at one time estimated to return to the creek. A page in Robert A. Brown’s The Story of the Arroyo Grande Creek describes how “steelhead would fill the creek as they propelled their great silvery bodies inland.” Trophy-sized, caught steelhead trout were regularly featured in local newspapers.
  • Decline After Lopez Dam
    The construction of Lopez Dam in the mid-1960s blocked access to the majority of the creek’s historic high-quality steelhead spawning and rearing habitat. Post-dam surveys have documented that the present steelhead population is a small remnant of what was once found in the creek, with at most in the low one hundred or even just dozens of adult steelhead now returning to the creek to attempt to spawn below the dam.
  • Recognition of Threatened Status
    By 1997, steelhead populations across California’s Central Coast, including Arroyo Grande Creek—were listed as threatened under the Endangered Species Act.

The County says it’s already complying and working with federal agencies to resolve the issue. Is this accurate?

Not exactly. The County is not currently in compliance with state or federal law: it still has not secured the required state water right license to operate Lopez Dam, despite nearly 30 years of discussions. It also has not secured the necessary permit under the Endangered Species Act to lawfully operate the dam. While County officials often claim they are “working with federal agencies,” in reality their efforts have amounted to little more than a “plan to make a plan.” For example, rather than committing to specific flow releases in line with agency recommendations, habitat improvements, or operational changes that would benefit steelhead, the County has largely only proposed additional studies and frameworks for future negotiations without adopting any enforceable measures that would actually protect steelhead or satisfy state water right licensing requirements. During this time, the County has continued to divert water from the creek without addressing the impacts on steelhead trout and other imperiled wildlife. Furthermore, as noted above, the County continues to try to contradict in court the overwhelming evidence that its Lopez Dam operations are jeopardizing steelhead survival, rather than devote its resources to finding a balanced solution for protecting steelhead while providing necessary water supply to local communities.

Until the County commits to enforceable measures that both secure a valid water right permit and protect threatened species as required by the Endangered Species Act, its claims of compliance remain misleading.

What would a real solution look like?

A real solution would bring Lopez Dam into compliance with the law by securing a valid state water right license that includes enforceable protections for steelhead trout and other wildlife, and by committing to a robust Habitat Conservation Plan that ensures the survival and recovery of all imperiled wildlife in Arroyo Grande Creek, including steelhead. This means committing to practical, science-based measures such as releasing sufficient water from Lopez Dam to support fish migration and spawning, restoring stream habitat downstream of the dam, and modernizing operations to balance human water needs with the health of our rivers. These actions are both feasible and necessary. By adopting them, the County could finally resolve its 30-year problem, protect threatened species, and provide lasting water security for the Five Cities.

What happens if the County keeps delaying in court?

If the County continues down the path of endless legal delays, Five Cities residents will keep paying millions of dollars in legal bills without getting any closer to a real solution. Every dollar spent on delay tactics in litigation is money that could otherwise fund completion of the environmental studies and habitat improvement projects that the County must perform to secure its water right, development of an adequate Habitat Conservation Plan, as well as projects to improve water efficiency and diversify water supply. Even if the lawsuit were to go away, the fundamental problem would remain: the County still lacks a valid water right license and still hasn’t addressed the dam’s impacts on steelhead. Until those issues are resolved, the problem of noncompliance with the law will not go away.

Who is responsible for making the final decision?

While residents of the Five Cities are paying all the legal bills through their water rates, the San Luis Obispo County Board of Supervisors has the ultimate authority over the ongoing litigation and any settlement decisions. This means the Supervisors could choose to end the wasteful legal delays at any time and direct resources toward compliance and environmental protection instead. Unfortunately, as long as the Board chooses to continue fighting in court while also failing to complete adequate environmental improvement plans needed to secure the necessary water right license for the dam, taxpayers in the Five Cities will keep bearing the financial burden.